Concrete Volume Calculator
Calculate the exact amount of concrete needed for a slab, column or footing. Results are given in cubic yards (for ready-mix ordering), cubic meters and number of 60 lb pre-mix bags. A 10% waste allowance is automatically included.
Your numbers
- Cubic meters
- 2.08 m³
- 60 lb bags
- 163 bags
- Cubic feet
- 73.33 ft³
How to calculate concrete for a slab, column or footing
Concrete is ordered by volume, so every shape comes down to cubic feet first. For a slab or footing, multiply length by width in feet, then multiply by the thickness or depth in inches divided by 12. For a round column, halve the diameter to get the radius and use the cylinder formula π x r² x h. The calculator then adds 10% for spillage, uneven ground and form flex. Cubic feet are divided by 27 to give cubic yards, which is how US ready-mix suppliers sell concrete, and the yardage is rounded up to the next hundredth so you never under-order. Cubic meters use 1 ft³ = 0.0283168 m³. For bags, the total is divided by 0.45 ft³, the typical yield of one 60 lb bag, and rounded up to a whole bag.
Slab: L x W x (thickness/12) | Column: π x r² x h | Add 10% for wasteWorked example. A 20 ft x 10 ft slab at 4 inches thick is 66.67 cubic feet before waste and 73.33 cubic feet with the 10% allowance. That is about 2.72 cubic yards (2.08 m³), or 163 bags of 60 lb concrete.
More worked examples
A 12 ft x 12 ft patio at 4 inches is 48 cubic feet, or 52.8 with waste: about 1.96 cubic yards, 1.50 m³ or 118 bags of 60 lb mix. A strip footing 10 ft long, 2 ft wide and 12 inches deep is 20 cubic feet, 22 with waste: about 0.82 cubic yards or 49 bags. A round column 1 ft across and 3 ft tall (a typical 12 inch tube form for a deck post) is about 2.36 cubic feet, 2.59 with waste, which is 6 bags. For several identical posts, multiply one post's volume by the count: four of those columns need about 10.37 cubic feet, or 24 bags. For a driveway, run each rectangular section separately and add the results.
Choosing the thickness
Thickness has the biggest effect on the order, because it multiplies the whole area. Common guidance is 4 inches for patios, walkways and shed floors, and 5 to 6 inches for driveways that carry cars, with thicker slabs and reinforcement for heavier vehicles. Going from 4 to 6 inches on a 10 ft x 10 ft slab raises the order from about 1.36 to 2.04 cubic yards. Every extra inch over 100 square feet adds about 8.3 cubic feet (0.31 cubic yards) before waste. Also check the real depth of your forms: a 2x4 laid on edge is only 3.5 inches tall, and a subgrade that is half an inch low across 200 square feet swallows another 8.3 cubic feet. Measure the depth at several points and use the average.
Bags or ready-mix truck?
Use bags for small jobs and a truck for anything big. One cubic yard is 27 cubic feet, which is 60 bags of 60 lb mix (about 3,600 lb to lift and mix by hand), 45 bags of 80 lb mix at 0.6 cubic feet each, or 90 bags of 40 lb mix. Below roughly one cubic yard, bags are usually simpler. Above that, ready-mix is faster and gives a more uniform pour, since a slab mixed in dozens of separate batches can cure unevenly. Many suppliers charge a short-load fee for orders under a few yards, so ask for the price at your exact volume. When you order, round up to the supplier's increment, often a quarter or half yard: running short mid-pour leaves a cold joint.
Questions people ask
How many bags of concrete make a cubic yard?
A cubic yard is 27 cubic feet. An 80 lb bag yields about 0.6 cubic feet, so you need about 45 bags, and a 60 lb bag yields about 0.45 cubic feet, so you need about 60 bags. Add a little extra for waste.
How many bags of concrete are in a cubic yard?
About 60 bags of 60 lb mix, 45 bags of 80 lb mix or 90 bags of 40 lb mix, based on typical yields of 0.45, 0.60 and 0.30 cubic feet per bag. Add your waste allowance on top.
When should I use ready-mix vs bags?
Use ready-mix for pours over about 1 cubic yard, because a truck is faster and gives more consistent quality than mixing 60 or more bags by hand. For small projects such as post holes, steps or a small pad, pre-mix bags are more convenient.
Why is 10% waste added?
Because real pours always use more than the drawing. Irregular formwork, spillage, uneven subgrade and forms bowing under the weight typically add 5 to 15% to the exact calculated volume, and 10% is the common buffer.
How much concrete do I need for a 10x10 slab?
A 10 ft x 10 ft slab at 4 inches thick needs about 1.36 cubic yards including 10% waste, or about 82 bags of 60 lb mix. At 6 inches thick it needs about 2.04 cubic yards.
Does the calculator handle circular slabs or stairs?
Not directly. For a round slab, use the column option with the slab diameter as the diameter and its thickness in feet as the height (4 inches is 0.33 ft). For steps, calculate each step as a small slab and add them.
Put this calculator on your site
Free to use on any site. Please keep the credit link.
<iframe
id="letmecalc-concrete-calculator"
src="https://letmecalc.com/embed/construction/concrete-calculator"
title="Concrete Calculator"
width="100%"
height="620"
style="border:0;max-width:100%"
loading="lazy"
></iframe>
<p><a href="https://letmecalc.com/construction/concrete-calculator" target="_blank" rel="noopener">Concrete Calculator</a> by letmecalc</p>
<script>
(function () {
var f = document.getElementById("letmecalc-concrete-calculator");
window.addEventListener("message", function (e) {
if (e.origin !== "https://letmecalc.com") return;
if (!f || e.source !== f.contentWindow) return;
var d = e.data;
if (!d || d.source !== "letmecalc-embed" || d.type !== "resize") return;
if (typeof d.height === "number" && d.height > 0) {
f.style.height = d.height + "px";
}
});
})();
</script>